Pengerjaan Breakwater Di Tiga Pulau Permukiman Terus Dikebut
.
photo Suparni - Beritajakarta.id

Breakwater Project in Seribu Islands Accelerated

The breakwater project in the waters of Panggang, Pramuka and Karya islands, Seribu Islands keeps being accelerated.

Our hope is we could finish it within three months

"From nine residential islands, construction process of the breakwater in three islands out of them is faster," said Head of Seribu Islands Water Management Sub-dept, Mustajab, Thursday (7/20).

Due to varied long, the construction progress is surely different. In details, the breakwater long in Panggang Islands is about 594 meters, Pramuka Island with 594 meters and Karya Island with 369 meters.

Breakwater in Seribu Islands must Be Tested

"Our hope is we could finish it within three months," he hoped.

Linked News
Popular News indeks
  1. Monas Prepares to Greet Visitors This Eid Holiday

    access_time30-03-2025 remove_red_eye716 personDessy Suciati
  2. Jakarta Vice Governor Rano Wishes a Happy Eid al-Fitr 1446 Hijri

    access_time31-03-2025 remove_red_eye603 personFolmer
  3. Foul Smell Around JGC Clarified Not Coming from Rorotan RDF

    access_time28-03-2025 remove_red_eye438 personAldi Geri Lumban Tobing
  4. Odd-Even Policy in Jakarta Put on Hold for Eid Break

    access_time28-03-2025 remove_red_eye326 personAldi Geri Lumban Tobing
  5. 49,101 Local and Foreign Tourists Swarm Monas

    access_time02-04-2025 remove_red_eye283 personBudhi Firmansyah Surapati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik