Pengerjaan Breakwater Di Tiga Pulau Permukiman Terus Dikebut
.
photo Suparni - Beritajakarta.id

Breakwater Project in Seribu Islands Accelerated

The breakwater project in the waters of Panggang, Pramuka and Karya islands, Seribu Islands keeps being accelerated.

Our hope is we could finish it within three months

"From nine residential islands, construction process of the breakwater in three islands out of them is faster," said Head of Seribu Islands Water Management Sub-dept, Mustajab, Thursday (7/20).

Due to varied long, the construction progress is surely different. In details, the breakwater long in Panggang Islands is about 594 meters, Pramuka Island with 594 meters and Karya Island with 369 meters.

Breakwater in Seribu Islands must Be Tested

"Our hope is we could finish it within three months," he hoped.

Linked News
Popular News indeks
  1. Transjakarta Officially Opens School for Bus Drivers

    access_time20-11-2024 remove_red_eye1045 personAldi Geri Lumban Tobing
  2. Acting Governor Teguh: Coastal Seawall Construction Begins in 2025

    access_time20-11-2024 remove_red_eye908 personFolmer
  3. Legislator Ahmad Lukman Jupiter Wants PT FSTJ Add Shop Cars

    access_time19-11-2024 remove_red_eye553 personDessy Suciati
  4. PMPTSP Agency Launches PIN Greenvest to Prompt Green and Sustainable Investment

    access_time21-11-2024 remove_red_eye449 personAldi Geri Lumban Tobing
  5. Transjakarta Extends its Operation to 11 PM Today

    access_time19-11-2024 remove_red_eye386 personAldi Geri Lumban Tobing